Maharashtra Cabinet approves over Rs 10,000 Cr rise in cost of Mumbai Metro Line 3

11 Aug 2022 10:35:38
Mumbai, August 11: The newly expanded Eknath Shinde cabinet in Maharashtra approved an additional expenditure of Rs 10,269 crore for the underground Mumbai Metro Line 3 project, at its first meeting.

Metro
 
Deputy CM Devendra Fadnavis made the announcement after the meeting. Speaking to reporters, he said, "The cost (of Mumbai Metro Line 3) has increased on account of almost no construction undertaken in the last two years. Hardly any construction work was carried out (under the previous Maha Vikas Aghadi government)."
 
 
This was the first cabinet meeting after its expansion on Tuesday when 18 new members - 9 each of the Shiv Sena faction led by CM Eknath Shinde and BJP - were inducted. He said, the cabinet approved an additional expenditure of Rs 10,000 crore for Mumbai Metro Line 3.

The original cost of the project was Rs 23,136 crore, which has now gone up to Rs 33,405 crore (total rise Rs 10,269 crore). The state is going to request the Union government to contribute from its corpus for the completion of the project.

Earlier, the state was supposed to spend Rs 2,402 crore which has now increased to Rs 3,699 crore. The cabinet instructed the Mumbai Metropolitan Regional Development Authority (MMRDA) to transfer Rs 1,297 crore (the difference in cost) to the Mumbai Metro Rail Corporation as part of the Rs 10,269 crore funding, he said.
 
Also Read | India's longest sea bridge Mumbai Trans Harbour Link to open by end of 2023
 
The Metro Line 3 is funded by Japan International Cooperation Agency (JICA) which would now increase its contribution from Rs 13,235 crore to Rs 19,924 crore, the deputy CM said. The Cabinet cleared a proposal to make a fresh demand to JICA to increase its loan amount, Fadnavis said.

The 33.5-km-long corridor running along Colaba-Bandra-SEEPZ (starting in south Mumbai and ending in suburban Andheri) will have 26 underground stations and one at-grade. By 2031, some 17 lakh passengers will travel by the Metro Line 3 every day. People can travel from Colaba (in south Mumbai) to the international airport in suburban Mumbai in 50 minutes, he said.

The tunnel work has been completed 98.6%, while 82.6% work on stations, too, has been done. Acquisition of 73.14 hectares of government land and another 2.56 hectares of private land has also been completed, he said.
Powered By Sangraha 9.0